Designated Water Line Construction Update

Type(s)
Village News

đźš§ Construction Updateđźš§

As part of the Fraser Lake Reservoir Fill Line, Utilities and Road Upgrades project, Dawson Civil is continuing work on Tunasa Drive and Tunasa Crescent.

 

📍 This week, Tunasa Crescent will be shut down between Park Drive and Chowsunket Street until Wednesday night. To access Park Dr, use Tunasa DràSimon Fraser AveàTunasa Cres. Graveling will continue on Carrier Crescent and Tunasa Crescent – avoid the area as much as possible. Water Tie-ins will be happening this week, there will be water service interruptions. Individuals residents will be notified if they will be affected.

 

Please note:

• Access to driveways will be temporarily restricted.
• Garbage collection – Please have cans out Tuesday night or before 7am on Wednesday morning.

• The road behind Mouse Mountain Elementary School is being used as a haul route for material. Please avoid this area during work hours Monday to Saturday 7am-5pm.

• Please avoid touching any valves or pressure test trees as they can be harmful when played with. 

 

đź”¶ Road Conditions
We understand the road conditions have been challenging. Our crews are doing their best to maintain safe and drivable access for residents throughout the construction period. However, due to fluctuating weather conditions—particularly rain—there may be times when surfaces are rough or muddy. Please drive slowly and carefully through the area, and we thank you for bearing with us as we work to improve the long-term infrastructure.

 

🌨 Winter Road Preparations
Please note that the road construction will not be fully completed this season. With colder weather approaching, we have received questions and concerns about how the roads will be left for winter. Our plan is to leave the roadway in a stable, graded, and passable condition until full paving and completion resume in the spring. We will ensure any exposed or soft areas are properly addressed to support winter maintenance such as snow clearing and sanding.

 

For questions or concerns, please contact our Community Liaison Nichole at 778-694-2117.

Thank you for your continued patience and cooperation as we complete this important infrastructure upgrade.