Construction work continues this week as crews make progress on road and infrastructure improvements throughout the project area. Please expect construction equipment, paving crews, personnel, and trucks to be active in the neighbourhood. Please note, paving is highly weather-dependent, and dates may change at short notice.
This week's construction activities include:
- October 7th – Tunasa Crescent
- October 8th – Carrier Crescent and Village Office Parking Lot
- October 9th–10th – Tunasa Drive
- October 11th – Extra day planned for weather interruptions (if needed).
- Swaling and culvert work will also continue on Tunasa Drive, and yard restoration will take place in areas impacted by construction. Please slow down and drive with caution through active work areas.
Residents may experience temporary delays, road restrictions, and changes to driveway access as work progresses. Crews will communicate directly with affected residents regarding any access impacts and parking requirements.
Thank you to residents and motorists for your continued patience and cooperation as we work to complete these road improvements.
🗑️ Garbage collection will continue as normal.