đźš§ PAVING UPDATE FOR TUNASA CRESCENT, CARRIER CRESCENT, & TUNASA DRIVEđźš§

Type(s)
Village News

The paving schedule has changed. Please see below for all updates that may impact access to your driveway. All dates are weather dependent and may change at short notice. Please expect construction equipment, paving crews, personnel, and trucks to be active in the neighbourhood. 

This week's construction activities include:

  • October 8th–9th – Tunasa Drive, including the Simon Fraser Ave cul-de-sac
  • October 10th – Tunasa Drive, crews will complete the Village Office Parking Lot, patching, Carrier Crescent, and asphalt driveways.
  • October 11th – Extra day planned for weather interruptions (if needed)

When the pavers are on your street, the entire road will be closed. Please have your vehicles out of your driveways by 7:00 am on the day your street is being paved. You will not be able to leave for approximately 2 hours once paving passes your driveway.

Please stay clear of paving activities. The pavers and equipment move quickly!

🗑️ Garbage collection will continue as normal.

Thank you for your cooperation,

📞 Questions or concerns?
Stephen Vickers - Community Liaison
250-608-8425