This notice is to inform you of the next phase of construction activities in your neighbourhood. Work on Tunasa Drive is continuing with the installation of the new storm main. Please note there will be an increase in construction equipment and personnel in the area as the project progresses.
The following activities are scheduled for this week:
-
Storm main installation from 515 Tunasa Drive to 568 Tunasa Drive.
Upcoming activities in the following weeks:
-
Construction operations and storm installation will be moving towards Tunasa Crescent.
Tunasa Drive will be limited to single-lane access to local traffic only during construction. Please utilize the traffic detour to avoid the work area where possible.
For your safety, please stay clear of the worksite and all construction equipment, and do not approach or enter the active construction zone. If you need to pass near the active construction zone, please contact Erek for assistance.
If you require further information or assistance, please don’t hesitate to contact the Community Liaison at the numbers listed below:
Jennie Preziosi
250-299-9508
Erek Boake
250-682-3239