🚧 YARD RESTORATION & SITE CLEANUP🚧

Work continues this week on Tunasa Drive, Tunasa Crescent and Carrier Crescent as the project moves into its final stages. All activities are weather dependent and may change on short notice.

This week's construction activities include:

  • Driveway paving: completing today, October 19th
  • Grading and shouldering: roadside ditches and drainage shaping, plus gravel along road edges.
  •  Grouting: underground utilities.
  • Yard restoration: topsoil and seeding on disturbed areas.
  • Line painting: crosswalks and stop bars coming soon. Date to be confirmed, and we’ll share an update as soon as we can.

As the project wraps up, crews and equipment are still working in the area. Please use caution in work zones and watch for workers and equipment that may move unexpectedly. Crews will communicate directly with affected residents regarding any access impacts.

Thank you to residents and motorists for your continued patience and cooperation as we wrap up this project.

🗑️ Garbage collection will continue as normal.

📞 Questions or concerns?
Stephen Vickers - Community Liaison
250-608-8425